What Happens When You Delete Baselined Data?

By Dale Howard, Microsoft Project MVP

Background Information

Question: What happens when you delete baselined data in a Microsoft Project schedule?

Answer: Nothing good.

When you deleted baselined data in a Microsoft Project schedule, you will introduce variance into the schedule in a way that the variance cannot be explained. I ran into this situation recently with a project manager who had deleted a resource from his schedule because the resource left the company. This action introduced variance anomalies that were almost beyond comprehension.

Our best practice recommendation is that you should never delete baselined data from a project schedule. This recommendation is for both types of project data: task data and resource data.

But what happens if you ignore these best practices and you delete either task data or resource data from a project? Let me show you.

Deleting Baselined Task Data

Figure 1 shows a project that is in progress with task updates entered through Friday, November 10. Notice the consistency of the variance data shown in the Cost Variance and Work Variance columns. Specifically notice that the Cost Variance value is $8,000 for the Phase I summary task, which is the sum of the Cost Variance values of its five subtasks ($1,600 + $4,800 + $1,600 + $0 + $0 = $8,000). Notice also that the Work Variance value is 160h for the Phase I summary task, which is the sum of the Work Variance values of its five subtasks (32h + 96h + 32h + 0h + 0h = 160h).

Figure 1: In-progress project with variance

With the completion of the Test P1 task, team members indicated that the Rebuild P1 task is no longer needed, as the testing revealed there are no problems that would necessitate a rebuild of the product. What do you think would happen if the project manager deletes the Rebuild P1 task in response? Figure 2 shows the same project after the project manager deleted the Rebuild P1 task and then relinked the Test P1 and Implement P1 tasks.

Figure 2: Project after deleting the Rebuild P1 task

Notice the inconsistency of the variance data shown in the Cost Variance and Work Variance columns. Notice that the Cost Variance value is -$24,000 for the Phase I summary task, which is not the sum of the Cost Variance values of its four subtasks. Notice also that the Work Variance value is -480h for the Phase I summary task, which is not the sum of the Work Variance values of its four subtasks. The variance numbers are totally out of sync between the subtasks and their summary task, and there is no way to explain why.

This is the reason for our best practice recommendation that you should never deleted a baselined task. If a task is no longer needed, our best practice recommendation is to cancel the task instead. In Microsoft Project Professional, you can use the Inactivate button in the Task ribbon to cancel the unneeded task. Figure 3 shows the same project, except with the Rebuild P1 task cancelled using the Inactivate feature instead of deleted.

Figure 3: Project after deleting the Rebuild P1 task

As a courtesy, I have inserted the Cost and Work columns in the project shown in Figure 3 so that you can see the consistency of the variance data shown in the Cost Variance and Work Variance columns. Notice that the Cost Variance value is -$24,000 for the Phase I summary task. How did Microsoft Project calculate this value? It is the sum of the Cost Variance values for the first four subtasks, minus the Cost of the cancelled task ($1,600 + $4,800 + $1,600 + $0 -$32,000 = -$24,000). Notice also that the Work Variance value is -480 for the Phase I summary task. How did Microsoft Project calculate this value? It is the sum of the Work Variance values for the first four subtasks, minus the Work of the cancelled task (32h + 96h + 32h + 0h -640h = -480h). By using the Inactivate feature in Microsoft Project Professional, the project manager has an “electronic paper trail” that shows the cancelled task and explains the reason for the variance.

Deleting Baselined Resource Data

When you delete a baselined resource from a project schedule in Microsoft Project, the variance anomalies get even crazier. Figure 4 shows the Resource Sheet view of the original project shown previously in Figure 1, but with grouping applied by the Type column. Notice that the total Cost Variance is $8,000 and the total Work Variance is 160h for all resources in the project.

Figure 4: Resource Sheet view of project team members

Suppose that Calvin Baker leaves the company after completing his work on the first three tasks in the project. What do you think would happen if the project manager completely deletes Calvin Baker in response, including all the actual work he has completed in the project? Figure 5 shows the Resource Sheet view of the project after the project manager deleted Calvin Baker from the project. Notice that the total Cost Variance value is now $6,000 and the total Work Variance value is 120h for all resources in the project. Especially notice that there is no evidence whatsoever that Calvin Baker was ever a team member in this project.

Figure 5: Resource Sheet view – Calvin Baker deleted

Figure 6 shows the Gantt Chart view of this project after completely deleting Calvin Baker from the project. Notice how the Cost Variance and Work Variance values for negative for every summary task and detailed task in this project. Especially notice that there is no way to explain why the variance values are negative.

Figure 6: Gantt Chart view – Calvin Baker deleted

Instead of deleting Calvin Baker, our best practice recommendation is for the project manager to reassign Calvin’s uncompleted work to another resource. Figure 7 shows the Resource Sheet view of the project after the project manager reassigned Calvin Baker’s task to a new team member named Pancho Boie. Notice how the Cost Variance and Work Variance values are negative for Calvin Baker, which is caused by reassigning his uncompleted work to Pancho Boie. For Pancho Boie, notice how his Cost Variance and Cost amounts are identical, and his Work Variance and Work amounts of identical. This is because his Work and Cost information was never baselined. In Microsoft Project, there is no way to baseline only selected resources, so there is nothing we can do to hide the Cost Variance and Work Variance data for Pancho Boie.

Figure 7 – Resource Sheet view – Calvin Baker’s uncompleted work reassigned

Figure 8 shows the Gantt Chart view of the project after reassigning the uncompleted work from Calvin Baker to Pancho Boie. Notice how the Cost Variance and Work Variance values are identical to those shown originally in Figure 1. This is because reassigning Calvin Baker’s uncompleted work did cause any Work or Cost changes to the tasks originally assigned to him, but which are now assigned to Pancho Boie. If Pancho Boie had a different cost rate than Calvin Baker, there would have been additional variance shown in the Cost Variance columns for the reassigned tasks, however.

Figure 8: Gantt Chart view – Calvin Baker’s uncompleted work reassigned

To sum up, the best practice recommendations we recommend you follow are these:

  • Never delete baselined tasks or resources, as doing so will create all types of variance anomalies in your projects which you cannot explain.
  • Instead of deleting an unneeded task that has been baselined, cancel the task instead using the Inactivate button in the Task ribbon.
  • Instead of deleting a baselined resource, reassign the resource’s uncompleted work to another team member.

About Dale Howard, Director of Education, Sensei Project Solutions

Dale Howard is a seasoned training professional who is approaching 30 years of technical training experience. He has taught students how to effectively use every version of Microsoft Project beginning with version 4.0 for Windows 95, and every version of the Microsoft EPM tool beginning with Project Central in the year 2000. Dale possesses the coveted Project MVP title and is one of only 64 Project MVPs in the entire world. He is the co-author of 20 books on Microsoft Project and Project Server. Dale is known for high-energy, highly interactive style of presenting and teaching. He was voted the “Best Presenter” by conference participants at the Project Conference in 2012.

 

 

 

 

 

 

 

About Sensei Project Solutions

Sensei Project Solutions, a Finalist for the 2017 Microsoft Project and Portfolio Management (PPM) Partner of the Year, focuses on bringing Instant Productivity to your team. Our mission is to help individuals and organizations be more productive so that they can achieve their greatest potential. As a Gold certified Microsoft Partner and Registered Education Provider (R.E.P.) with the Project Management Institute (PMI®), Sensei offers a complete set of services and products for a successful Microsoft PPM deployment. Our guiding principles for Proactive PPM follow best practices and industry standards aligned with the Project Management Institute (PMI) and Gartner, enabling organizations to manage resource demand, obtain business intelligence that facilitates better decision making, increase business effectiveness by easily connecting people, and become self-sufficient with PPM processes and solutions. In short, Sensei helps organizations achieve Instant Productivity.

Stay up to date with insights from the Sensei Blog

  • This field is for validation purposes and should be left unchanged.